Construction updates

The Valley Creek Bridge replacement project in Stillwater County is funded with a grant from the Montana Coal Endowment Program (MCEP) with matching funds grant from 
the Montana Department of Transportation / Senate Bill 536. Stillwater County is utilizing the GC/CM construction method for a streamlined project with the contract being awarded to TCA Group
.  Construction on the bridge is anticipated to begin in mid-October of 2024 with an anticipated completion date of late December 2024.

1000004610.jpg
1000004608.jpg
GetAttachmentThumbnail.jpg
IMG_1458.JPEG
IMG_1458.JPEG
IMG_1415.jpeg

Update 1/6/25

The bridge is open, project is in winter shut down currently. The future task will be pulling the detour bridge.

​

​

Update 11/29/24

The concrete was covered with insulated blankets and heated during the curing period. The crew was off for Thanksgiving, but back on site Monday.

Update 11/19/24

The pile drive was completed according to plan and the crew spent Sunday and Monday building forms for the concrete abutments, which were then poured.

Update 11/11/24

Crews have excavated and compacted the area for the concrete caps, as well as the rip rap slopes. The rip rap and driving pile are being replaced this week.

​

​

Update 10/27/24

Detour bridge and road has been installed and traffic has been moved over for the project. Demolition of existing bridge coming this week.

Update 10/4/24

Bridge Mobilization begins 10/14