top of page
Stitched Photo - 1.jpg

construction updates

Construction on the new truss bridge began in January of 2024 with an anticipated completion date of September 2024. Construction was awarded to Battle Ridge Builders. This project is being funded by FEMA and State of Montana DES.

Carbella Closure Map.jpg

CLOSURE UPDATE

During the construction of the Carbella Bridge by Park County and its contractor, Battle Ridge Builders, access is closed to the public. A designated viewing area is available on BLM land for observing the bridge assembly.

This closure is essential to facilitate BRB's activities, including offloading, assembling, and installing the new truss superstructure onto the bridge foundation.

For safety reasons, please do not cross barriers and avoid parking along the County road.

For more information contact:
Nate Peressini, PE - Project Manager
(406) 522-8594 or subscribe to this site for further updates.

Carbella_Bridge_Update_050424.jpg

Update 5/3/2024

Current Work

  • Continued assembly of truss superstructure.

  • Placement and compaction and bridge end backfill.

Work Planned

  • Continue assembling truss superstructure.

Upcoming Meetings/Milestones

  • Setting of truss members on foundation.

Carbella_Bridge_Update_042724.jpg

Update 4/26/2024

Current Work

  • Continued assembly of truss superstructure.

  • Placement and compaction and bridge end backfill.

Work Planned

  • Continue assembling truss superstructure.

  • Continue delivery of bridge superstructure.

Upcoming Meetings/Milestones

  • Setting of truss members on foundation.

Carbella_Bridge_Update_042024.jpg

Update 4/19/2024

Current Work

  • Concrete completed on western (bent #2) abutment.

  • Assembly of truss superstructure has begun.

Work Planned

  • Continue assembling truss superstructure.

  • Continue delivery of bridge superstructure.

Upcoming Meetings/Milestones

  • Setting of truss members on foundation.

Carbella_Bridge_Update_041324.jpg

Update 4/12/2024

Current Work

  • Concrete completed on eastern (bent #1) abutment.

  • Concrete placed in bridge cap on western (bent #2) abutment.

Work Planned

  • Placement of concrete in backwall and wingwalls of bent #2.

  • Delivery of bridge superstructure begins.

Upcoming Meetings/Milestones

  • Assembly of bridge superstructure.

Carbella_Bridge_Update_040624.jpg

Update 4/5/2024

Current Work

  • Concrete abutment laid out on western (bent #2) abutment.

  • Concrete placed in bridge cap on eastern (bent #1) abutment.

  • Pile driving completed on bent #2 abutment.

Work Planned

  • Placement of concrete in backwall and wingwalls of bent #1.

  • Tie rebar and install concrete cap forms on Bent #1.

  • Placement of concrete in bridge cap on bent #2.

Upcoming Meetings/Milestones

  • Tie rebar and install concrete forms for backwall and wingwalls on bent #2.

  • Delivery of bridge superstructure.

Screenshot 2024-03-25 084103.png

Update 3/22/2024

Current Work

  • Concrete abutment laid out on (bent #1) abutment.

Work Planned

  • Mobilize pile driving equipment to western (bent #2) abutment.

Upcoming Meetings/Milestones

  • Complete pile foundation installation on bent #2 over approximately the next couple weeks.

  • Tie rebar and install concrete forms on Bent #1.

Carbella_Bridge_Update_031524.jpg

Update 3/15/2024

Current Work

  • Pile driving completed on eastern (bent #1) abutment.

Work Planned

  • Mobilize pile driving equipment to western (bent #2) abutment.

Upcoming Meetings/Milestones

  • Complete pile foundation installation on bent #2 over approximately the next couple weeks.

  • Tie rebar and install concrete forms on Bent #1.

Carbella_Bridge_Update_030824.jpg

Update 3/8/2024

Current Work

  • Drill in piling completed on both bridge abutments.

  • Pile driving started on eastern (bent #1) abutment.

Work Planned

  • Continue pile driving on eastern (bent #1) abutment.

  • Upon completion of pile driving on bent #1, begin pile driving on western (bent #2) abutment.

Upcoming Meetings/Milestones

  • Complete pile foundation installation over approximately the next couple weeks.

Carbella_Bridge_Update_030124.jpg

Update 3/1/2024

Current Work

  • Half the pipe pile (two) drilled into minimum depth on western (bent #2) abutment.

Work Planned

  • Mobilize crane and pile hammer to drive in pipe pile on eastern (bent #1) abutment.

  • Continue drilling in piling on western (bent #2) abutment.

Upcoming Meetings/Milestones

  • Complete pile foundation installation over approximately the next couple weeks.

Carbella_Bridge_Update_022424.jpg
Carbella_Bridge_Update_020224.jpg

Update 2/2/2024

Current Work

  • Demolition of existing abutments.

  • Installation of riprap armoring.

Work Planned

  • Install river signage at upstream and downstream fishing accesses.

  • Mobilize drill-in piling equipment to the project.

  • General clean up and phasing items - anticipated for week of 2/5.

  • Start of drilled in piling for foundation - anticipated for week of 2/12.

Upcoming Meetings/Milestones

  • Begin pile foundation installation over approximately the next month.

Update 2/23/2024

Current Work

  • Demolition of existing abutments.

  • Installation of riprap armoring.

Work Planned

  • Install river signage at upstream and downstream fishing accesses.

  • Mobilize drill-in piling equipment to the project.

  • General clean up and phasing items - anticipated for week of 2/5.

  • Start of drilled in piling for foundation - anticipated for week of 2/12.

Upcoming Meetings/Milestones

  • Begin pile foundation installation over approximately the next month.

Bridge schematic.png

Update 1/31/2024

Current Work

  • Demolition complete.

  • Rip rap installed.

Work Planned

  • General clean up and phasing items - anticipated for week of 2/5.

  • Start of drilled in piling for foundation - anticipated for week of 2/12.

Upcoming Meetings/Milestones

  • Onsite meeting - 2/2/24

bottom of page